Hut 8 Beacon Point AI Data Center Campus
Under construction
United States · 2 projects · Last reported
Summary
Hut 8 Beacon Point AI data center campus
Hut 8 AI data center campus on about 521 acres in Nueces County, Texas, backed by 1,000 MW of utility capacity under an AEP Texas interconnection agreement. In 2026 Hut 8 signed two 15-year leases of 352 MW of IT capacity each with one unnamed high-investment-grade tenant, for 704 MW in total, worth about USD 9.8 billion each in base-term value. Hut 8 said in July 2026 that phase 1 construction had begun and phase 2 site preparation was under way; initial energization is targeted for Q1 2027 and the first phase 2 data hall for Q2 2028.
Source record as of 2026-08-04 · Details and sources
Hut 8 Beacon Point First Phase 352 MW Critical IT Lease
The August 4 update identifies active construction at Beacon Point and specifically reports Phase 1 and campus-substation work underway. Energization and first-hall delivery remain 2027 forecasts. evidence
Hut 8 Corp. · published 2026-08-04
Location
The interactive map needs JavaScript. Display anchor: 27.83452, -97.61476 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Campus reference; individual project footprints are not mapped.
Projects (2)
Hut 8 Beacon Point AI data center campus
Under construction last observed as of · Reported status
Location: Nueces County, Texas, US. Filings name Nueces County only, with no town, address or parcel. Coordinates are the Nueces County point from its Wikipedia article. Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR; Wikipedia
Use: Ai unspecified
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Power capacity | 1,000 MW | Contracted · Campus · Grid connection | 2026-07-20 | Utility capacity secured under an interconnection agreement with AEP Texas; Hut 8 calls Beacon Point a 1 GW campus on this basis. | Hut 8 Corp. via SEC EDGAR; The Energy Mag |
| Power capacity | 704 MW | Contracted · Campus · It load | 2026-07-20 | IT capacity leased to the single tenant across both phases after the second lease. | Hut 8 Corp. via SEC EDGAR |
| Power capacity | 352 MW | Under construction · Phase · It load · Phase 1 (six data halls) | 2026-07-20 | Critical IT capacity of the first leased data center, across six data halls. The Energy Mag reports that a redesign raised the first building from 224 MW to 352 MW without more land or utility capacity. | Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR; Hut 8; The Energy Mag |
| Power capacity | about 500 MW | Contracted · Phase · Grid connection · Phase 1 | 2026-05-06 | Share of the 1,000 MW utility capacity supporting the first 352 MW IT phase. | The Energy Mag |
| Power capacity | 352 MW | Contracted · Phase · It load · Phase 2 | 2026-07-20 | Second 15-year lease with the same tenant; site preparation under way and long-lead equipment procured. | Hut 8 Corp. via SEC EDGAR |
| Power capacity | 500 MW | Under construction · Phase · Grid connection · Phase 2 | 2026-08-04 | Utility capacity for phase 2, which Hut 8 moved into its energy-capacity-under-construction category after 30 June 2026; it needs no capacity beyond the campus interconnection. | Hut 8 Corp. via SEC EDGAR; Hut 8 |
| Land area | about 521 acres | Reported · Campus | 2026-06-04 | Hut 8 Corp. via SEC EDGAR |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Hut 8 | Developer | Develops the campus through its wholly owned subsidiary Beacon Point DC LLC, which issued the project notes. | Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR; Hut 8 |
| AEP Texas | Utility | Provides electric delivery service under the campus interconnection agreement. | Hut 8 Corp. via SEC EDGAR; The Energy Mag |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2026-05-06 | Announced | Actual | Hut 8 announced the first 15-year, 352 MW IT lease, commercializing phase 1 of the campus. | Hut 8; The Energy Mag |
| 2026-06-09 | Other | Actual | Hut 8 closed USD 4.25 billion of investment-grade project notes to finance construction of the Beacon Point data center. | Hut 8 |
| 2026-07-20 | Expansion announced | Actual | Second 352 MW IT lease signed with the existing tenant, fully committing the campus utility capacity. Hut 8 said phase 1 construction had already begun. | Hut 8 Corp. via SEC EDGAR |
| 2027-Q1 | Other | Planned | Target for initial energization of the first phase. | Hut 8 Corp. via SEC EDGAR; The Energy Mag |
| 2027-Q3 | First operational | Planned | Target for delivery of the first data hall, as reported by The Energy Mag. | The Energy Mag |
| 2028-Q2 | Other | Planned | Target for delivery of the first phase 2 data hall. | Hut 8 Corp. via SEC EDGAR |
Power supply
| Type | Description | Sources |
|---|---|---|
| Grid | Grid supply from AEP Texas under a 1,000 MW interconnection agreement, with a substation being built on the property as part of the phase 1 project. | Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR |
The tenant is not named; Hut 8 describes it as a high-investment-grade company (rated AA- or higher in the notes offering). Leases are triple-net with 15-year base terms worth USD 19.6 billion for the campus. Phase 1 is financed with USD 4.25 billion of non-recourse project notes issued by Beacon Point DC LLC; this is debt financing, not a disclosed project cost. The Energy Mag reports the site was first underwritten for affiliated miner American Bitcoin; Hut 8's releases opened do not say so. Hut 8 names AEP, Vertiv and Jacobs as delivery-model counterparties and an NVIDIA DSX reference design. The 1 GW label refers to utility capacity, not IT load.
Sources for these details
- Hut 8 announces pricing of $4.25 billion of investment-grade senior secured notes for Beacon Point data center project (Form 8-K, Exhibit 99.1) — Hut 8 Corp. via SEC EDGAR; 2026-06-04
- Hut 8 fully commercializes 1 GW Beacon Point AI data center campus with second 352 MW IT lease, bringing campus-level base-term contract value to $19.6 billion (Form 8-K, Exhibit 99.1) — Hut 8 Corp. via SEC EDGAR; 2026-07-20
- Hut 8 commercializes first phase of 1 GW Beacon Point AI data center campus with 15-year, 352 MW IT lease — Hut 8; 2026-05-06
- Hut 8 Surges 30% After Landing Second AI Data Center Lease Worth $9.8 Billion — The Energy Mag; 2026-05-06
- Hut 8 reports second quarter 2026 results — Hut 8; 2026-08-04 · Archived source
- Hut 8 closes $4.25 billion of investment-grade senior secured notes for Beacon Point data center project — Hut 8; 2026-06-09
- Nueces County, Texas — Wikipedia; publication date not stated
- Companies
Source and location review
- Status source
- Hut 8 fully commercializes 1 GW Beacon Point AI data center campus with second 352 MW IT lease, bringing campus-level base-term contract value to $19.6 billion (Form 8-K, Exhibit 99.1) evidence row
Hut 8 Corp. via SEC EDGAR · published 2026-07-20 · Regulatory filing - Locator
- County or district reference only · Compiled location reference · admin2 evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 84 days before the data update on 2026-10-27
Hut 8 Beacon Point First Phase 352 MW Critical IT Lease
Under construction last observed as of · Authoritative status update
Source and location review
- Status source
- Hut 8 August 4 Beacon Point physical construction update evidence row
Hut 8 Corp. · published 2026-08-04 · Company disclosure - Locator
- Campus locator · Official source · operator_published_campus_reference_point evidence
- Source checks
Not reviewed against imagery not_
reviewed_ for_ core_ preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 84 days before the data update on 2026-10-27
Location details
- Coordinates
- 27.83452, -97.61476
- Geometry licence
- IETF-Trust-Legal-Provisions, all-rights-reserved
- Use scope
- Campus locator
- Scope class
- operator_published_campus_reference_point
- Authority
- Official source
- Source entity
- Campus
- Method
- operator_published_mapbox_campus_marker
- Derivation
- Match direct campus page to the platform's same title and slug; dereference explicit geolocation fields; reproduce the site's six-decimal marker rounding; emit longitude then latitude.
- Precision scope
- Exact operator-rendered named campus marker, not a survey, campus boundary, building centroid, construction footprint, or phase-specific location.
- Horizontal uncertainty
Not reported
Publisher reports no bounded horizontal positional accuracy; decimal places and deterministic rounding do not establish site accuracy.
- Geometry evidence
- 111e4ef0 649edbaf 68bba6b3 873a0c1d ebef4446
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Beacon Point named operator record and coordinate Archived copy | Hut 8 Corp. Company disclosure | Geometry identity context, Site distinctness context, Geometry | not stated | all-rights-reserved | Hut 8 Corp. | 3535040f7761f2494fff88da0e16b5c60cfc1d3fdfe5a092bf1d2fd56847139bRetained source material; see source provenance | |
| Hut 8 announces pricing of $4.25 billion of investment-grade senior secured notes for Beacon Point data center project (Form 8-K, Exhibit 99.1) Archived copy | Hut 8 Corp. via SEC EDGAR Regulatory filing | Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Power Source: Grid, Role: Developer | source-terms-not-recorded | Hut 8 Corp. via SEC EDGAR | 0bd16c56aed073725bcc665eda5a666f7ad515bb58a4bd0e0df7023c87b901ccFactual source record; not the publisher page | ||
| Hut 8 August 4 Beacon Point physical construction update Archived copy | Hut 8 Corp. Company disclosure | Geometry identity context, Site distinctness context, Physical status | all-rights-reserved | Hut 8 Corp. | 5dd5a6ba19bde75372b8a39ab725d97fbd8429e8369a7f1d14ad47942c3e1b58Retained source material; see source provenance | ||
| Hut 8 closes $4.25 billion of investment-grade senior secured notes for Beacon Point data center project Archived copy | Hut 8 Company disclosure | Imported: Record, Milestone: Other | source-terms-not-recorded | Hut 8 | 332a8901e21c2ee73688143468c3b92fb0b46898868725593e23b3361bac89d4Factual source record; not the publisher page | ||
| Hut 8 commercializes first phase of 1 GW Beacon Point AI data center campus with 15-year, 352 MW IT lease Archived copy | Hut 8 Company disclosure | Imported: Record, Metric: Power Capacity, Milestone: Announced, Role: Developer | source-terms-not-recorded | Hut 8 | 629055a43e5a8458098dc4817c342f489bdb959ebd0cce74741d29280cb5eec1Factual source record; not the publisher page | ||
| Hut 8 frontend named marker derivation Archived copy | Hut 8 Corp. Company disclosure | Site distinctness context, Geometry | not stated | all-rights-reserved | Hut 8 Corp. | 832b2a3b34eb077b91faeb7bd5d3575f884ab65d1544dfa8d741bd78f29a4d8eRetained source material; see source provenance | |
| Hut 8 fully commercializes 1 GW Beacon Point AI data center campus with second 352 MW IT lease, bringing campus-level base-term contract value to $19.6 billion (Form 8-K, Exhibit 99.1) Archived copy | Hut 8 Corp. via SEC EDGAR Regulatory filing | Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Expansion Announced, Milestone: Other, Power Source: Grid, Role: Developer, Role: Utility | source-terms-not-recorded | Hut 8 Corp. via SEC EDGAR | 47785db84316bb58200e430420a28dbdcfa23d6975c53e2a5f72e7ba0f6d77b1Factual source record; not the publisher page | ||
| Hut 8 platform list binds named campuses to map locations Archived copy | Hut 8 Corp. Company disclosure | Geometry identity context, Site distinctness context, Geometry | not stated | all-rights-reserved | Hut 8 Corp. | 90ed067c4fb5f3998d9528e70a84ab1b6c24414084a00c42abfa432c855a3a19Retained source material; see source provenance | |
| Hut 8 reports second quarter 2026 results Archived copy | Hut 8 Company disclosure | Imported: Record, Imported: Status, Metric: Power Capacity | source-terms-not-recorded | Hut 8 | bf5b369cdc946027876265d781defe4c5a041aa71ff59fa6714445dc42ea2d18Factual source record; not the publisher page | ||
| Hut 8 Surges 30% After Landing Second AI Data Center Lease Worth $9.8 Billion Archived copy | The Energy Mag News | Imported: Record, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Milestone: Other, Role: Utility | source-terms-not-recorded | The Energy Mag | dbc391463fcf3234348b30a149ec70034b4c82ec1d7d865a02c48ddef5f2d6f5Factual source record; not the publisher page | ||
| Hut 8 website rights notice Archived copy | Hut 8 Corp. Company disclosure | Geometry identity context, Site distinctness context | not stated | all-rights-reserved | Hut 8 Corp. | baa8e25485074c69867e1eb23cff4111b0c36a3908b332ae1134644331b03549Retained source material; see source provenance | |
| Mapbox LngLat geographic coordinate contract Archived copy | Mapbox Company disclosure | Site distinctness context, Geometry | not stated | all-rights-reserved | Mapbox | 65696f2eadafcb1d2e7fc7e9f7c85bb923c0a3f428fb204047e0912890312cc0Retained source material; see source provenance | |
| Nueces County, Texas Archived copy | Wikipedia Other | Imported: Geometry, Imported: Record | not stated | source-terms-not-recorded | Wikipedia | 0ed0d7e8a77cbac2e7a7200955c8f36fa3e7d34777be3d9999dc7e5e11d8dd21Factual source record; not the publisher page | |
| RFC 7946 GeoJSON coordinate reference system Archived copy | IETF Trust Company disclosure | Site distinctness context, Geometry | not stated | IETF-Trust-Legal-Provisions | IETF Trust | bcaa061faa3f2f3eec2a5846b01e6986a6aacf7fa64c2e88f74fb02d260a1adfRetained source material; see source provenance |