Hut 8 Beacon Point AI Data Center Campus

Under construction

United States · 2 projects · Last reported

Summary

Hut 8 Beacon Point AI data center campus

Hut 8 AI data center campus on about 521 acres in Nueces County, Texas, backed by 1,000 MW of utility capacity under an AEP Texas interconnection agreement. In 2026 Hut 8 signed two 15-year leases of 352 MW of IT capacity each with one unnamed high-investment-grade tenant, for 704 MW in total, worth about USD 9.8 billion each in base-term value. Hut 8 said in July 2026 that phase 1 construction had begun and phase 2 site preparation was under way; initial energization is targeted for Q1 2027 and the first phase 2 data hall for Q2 2028.

Source record as of 2026-08-04 · Details and sources

Hut 8 Beacon Point First Phase 352 MW Critical IT Lease

The August 4 update identifies active construction at Beacon Point and specifically reports Phase 1 and campus-substation work underway. Energization and first-hall delivery remain 2027 forecasts. evidence

Hut 8 Corp. · published 2026-08-04

Location

The interactive map needs JavaScript. Display anchor: 27.83452, -97.61476 (Point locator, WGS 84).

View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser

Campus reference; individual project footprints are not mapped.

Projects (2)

Hut 8 Beacon Point AI data center campus

Under construction last observed as of · Reported status

Location: Nueces County, Texas, US. Filings name Nueces County only, with no town, address or parcel. Coordinates are the Nueces County point from its Wikipedia article. Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR; Wikipedia

Use: Ai unspecified

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Power capacity1,000 MWContracted · Campus · Grid connection2026-07-20Utility capacity secured under an interconnection agreement with AEP Texas; Hut 8 calls Beacon Point a 1 GW campus on this basis.Hut 8 Corp. via SEC EDGAR; The Energy Mag
Power capacity704 MWContracted · Campus · It load2026-07-20IT capacity leased to the single tenant across both phases after the second lease.Hut 8 Corp. via SEC EDGAR
Power capacity352 MWUnder construction · Phase · It load · Phase 1 (six data halls)2026-07-20Critical IT capacity of the first leased data center, across six data halls. The Energy Mag reports that a redesign raised the first building from 224 MW to 352 MW without more land or utility capacity.Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR; Hut 8; The Energy Mag
Power capacityabout 500 MWContracted · Phase · Grid connection · Phase 12026-05-06Share of the 1,000 MW utility capacity supporting the first 352 MW IT phase.The Energy Mag
Power capacity352 MWContracted · Phase · It load · Phase 22026-07-20Second 15-year lease with the same tenant; site preparation under way and long-lead equipment procured.Hut 8 Corp. via SEC EDGAR
Power capacity500 MWUnder construction · Phase · Grid connection · Phase 22026-08-04Utility capacity for phase 2, which Hut 8 moved into its energy-capacity-under-construction category after 30 June 2026; it needs no capacity beyond the campus interconnection.Hut 8 Corp. via SEC EDGAR; Hut 8
Land areaabout 521 acresReported · Campus2026-06-04Hut 8 Corp. via SEC EDGAR

Companies and organizations

NameRoleNotesSources
Hut 8DeveloperDevelops the campus through its wholly owned subsidiary Beacon Point DC LLC, which issued the project notes.Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR; Hut 8
AEP TexasUtilityProvides electric delivery service under the campus interconnection agreement.Hut 8 Corp. via SEC EDGAR; The Energy Mag

Timeline

DateEventActual or plannedNotesSources
2026-05-06AnnouncedActualHut 8 announced the first 15-year, 352 MW IT lease, commercializing phase 1 of the campus.Hut 8; The Energy Mag
2026-06-09OtherActualHut 8 closed USD 4.25 billion of investment-grade project notes to finance construction of the Beacon Point data center.Hut 8
2026-07-20Expansion announcedActualSecond 352 MW IT lease signed with the existing tenant, fully committing the campus utility capacity. Hut 8 said phase 1 construction had already begun.Hut 8 Corp. via SEC EDGAR
2027-Q1OtherPlannedTarget for initial energization of the first phase.Hut 8 Corp. via SEC EDGAR; The Energy Mag
2027-Q3First operationalPlannedTarget for delivery of the first data hall, as reported by The Energy Mag.The Energy Mag
2028-Q2OtherPlannedTarget for delivery of the first phase 2 data hall.Hut 8 Corp. via SEC EDGAR

Power supply

TypeDescriptionSources
GridGrid supply from AEP Texas under a 1,000 MW interconnection agreement, with a substation being built on the property as part of the phase 1 project.Hut 8 Corp. via SEC EDGAR; Hut 8 Corp. via SEC EDGAR

The tenant is not named; Hut 8 describes it as a high-investment-grade company (rated AA- or higher in the notes offering). Leases are triple-net with 15-year base terms worth USD 19.6 billion for the campus. Phase 1 is financed with USD 4.25 billion of non-recourse project notes issued by Beacon Point DC LLC; this is debt financing, not a disclosed project cost. The Energy Mag reports the site was first underwritten for affiliated miner American Bitcoin; Hut 8's releases opened do not say so. Hut 8 names AEP, Vertiv and Jacobs as delivery-model counterparties and an NVIDIA DSX reference design. The 1 GW label refers to utility capacity, not IT load.

Sources for these details
Companies
  • Developer: Hut 8 (unknown scope) evidence
  • Developer: Hut 8 (unknown scope) evidence
  • Developer: Hut 8 (unknown scope) evidence
  • Utility: AEP Texas (unknown scope) evidence
  • Utility: AEP Texas (unknown scope) evidence
Source and location review
Status source
Hut 8 fully commercializes 1 GW Beacon Point AI data center campus with second 352 MW IT lease, bringing campus-level base-term contract value to $19.6 billion (Form 8-K, Exhibit 99.1) evidence row
Hut 8 Corp. via SEC EDGAR · published 2026-07-20 · Regulatory filing
Locator
County or district reference only · Compiled location reference · admin2 evidence
Source checks

Not reviewed against imagery not_reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 84 days before the data update on 2026-10-27

Hut 8 Beacon Point First Phase 352 MW Critical IT Lease

Under construction last observed as of · Authoritative status update

Source and location review
Status source
Hut 8 August 4 Beacon Point physical construction update evidence row
Hut 8 Corp. · published 2026-08-04 · Company disclosure
Locator
Campus locator · Official source · operator_published_campus_reference_point evidence
Source checks

Not reviewed against imagery not_reviewed_for_core_preview
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verification

Status age at review: 84 days before the data update on 2026-10-27

Location details
Coordinates
27.83452, -97.61476
Geometry licence
IETF-Trust-Legal-Provisions, all-rights-reserved
Use scope
Campus locator
Scope class
operator_published_campus_reference_point
Authority
Official source
Source entity
Campus
Method
operator_published_mapbox_campus_marker
Derivation
Match direct campus page to the platform's same title and slug; dereference explicit geolocation fields; reproduce the site's six-decimal marker rounding; emit longitude then latitude.
Precision scope
Exact operator-rendered named campus marker, not a survey, campus boundary, building centroid, construction footprint, or phase-specific location.
Horizontal uncertainty
Not reported

Publisher reports no bounded horizontal positional accuracy; decimal places and deterministic rounding do not establish site accuracy.

Geometry evidence
111e4ef0 649edbaf 68bba6b3 873a0c1d ebef4446

A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.

Evidence

Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.

Evidence for Hut 8 Beacon Point AI Data Center Campus
TitlePublisherRolesPublishedRetrievedLicenceAttributionContent hash (SHA-256)
Beacon Point named operator record and coordinate
Archived copy
Hut 8 Corp.
Company disclosure
Geometry identity context, Site distinctness context, Geometrynot statedall-rights-reservedHut 8 Corp.3535040f7761f2494fff88da0e16b5c60cfc1d3fdfe5a092bf1d2fd56847139b
Retained source material; see source provenance
Hut 8 announces pricing of $4.25 billion of investment-grade senior secured notes for Beacon Point data center project (Form 8-K, Exhibit 99.1)
Archived copy
Hut 8 Corp. via SEC EDGAR
Regulatory filing
Imported: Geometry, Imported: Record, Metric: Land Area, Metric: Power Capacity, Power Source: Grid, Role: Developersource-terms-not-recordedHut 8 Corp. via SEC EDGAR0bd16c56aed073725bcc665eda5a666f7ad515bb58a4bd0e0df7023c87b901cc
Factual source record; not the publisher page
Hut 8 August 4 Beacon Point physical construction update
Archived copy
Hut 8 Corp.
Company disclosure
Geometry identity context, Site distinctness context, Physical statusall-rights-reservedHut 8 Corp.5dd5a6ba19bde75372b8a39ab725d97fbd8429e8369a7f1d14ad47942c3e1b58
Retained source material; see source provenance
Hut 8 closes $4.25 billion of investment-grade senior secured notes for Beacon Point data center project
Archived copy
Hut 8
Company disclosure
Imported: Record, Milestone: Othersource-terms-not-recordedHut 8332a8901e21c2ee73688143468c3b92fb0b46898868725593e23b3361bac89d4
Factual source record; not the publisher page
Hut 8 commercializes first phase of 1 GW Beacon Point AI data center campus with 15-year, 352 MW IT lease
Archived copy
Hut 8
Company disclosure
Imported: Record, Metric: Power Capacity, Milestone: Announced, Role: Developersource-terms-not-recordedHut 8629055a43e5a8458098dc4817c342f489bdb959ebd0cce74741d29280cb5eec1
Factual source record; not the publisher page
Hut 8 frontend named marker derivation
Archived copy
Hut 8 Corp.
Company disclosure
Site distinctness context, Geometrynot statedall-rights-reservedHut 8 Corp.832b2a3b34eb077b91faeb7bd5d3575f884ab65d1544dfa8d741bd78f29a4d8e
Retained source material; see source provenance
Hut 8 fully commercializes 1 GW Beacon Point AI data center campus with second 352 MW IT lease, bringing campus-level base-term contract value to $19.6 billion (Form 8-K, Exhibit 99.1)
Archived copy
Hut 8 Corp. via SEC EDGAR
Regulatory filing
Imported: Geometry, Imported: Record, Imported: Status, Metric: Power Capacity, Milestone: Expansion Announced, Milestone: Other, Power Source: Grid, Role: Developer, Role: Utilitysource-terms-not-recordedHut 8 Corp. via SEC EDGAR47785db84316bb58200e430420a28dbdcfa23d6975c53e2a5f72e7ba0f6d77b1
Factual source record; not the publisher page
Hut 8 platform list binds named campuses to map locations
Archived copy
Hut 8 Corp.
Company disclosure
Geometry identity context, Site distinctness context, Geometrynot statedall-rights-reservedHut 8 Corp.90ed067c4fb5f3998d9528e70a84ab1b6c24414084a00c42abfa432c855a3a19
Retained source material; see source provenance
Hut 8 reports second quarter 2026 results
Archived copy
Hut 8
Company disclosure
Imported: Record, Imported: Status, Metric: Power Capacitysource-terms-not-recordedHut 8bf5b369cdc946027876265d781defe4c5a041aa71ff59fa6714445dc42ea2d18
Factual source record; not the publisher page
Hut 8 Surges 30% After Landing Second AI Data Center Lease Worth $9.8 Billion
Archived copy
The Energy Mag
News
Imported: Record, Metric: Power Capacity, Milestone: Announced, Milestone: First Operational, Milestone: Other, Role: Utilitysource-terms-not-recordedThe Energy Magdbc391463fcf3234348b30a149ec70034b4c82ec1d7d865a02c48ddef5f2d6f5
Factual source record; not the publisher page
Hut 8 website rights notice
Archived copy
Hut 8 Corp.
Company disclosure
Geometry identity context, Site distinctness contextnot statedall-rights-reservedHut 8 Corp.baa8e25485074c69867e1eb23cff4111b0c36a3908b332ae1134644331b03549
Retained source material; see source provenance
Mapbox LngLat geographic coordinate contract
Archived copy
Mapbox
Company disclosure
Site distinctness context, Geometrynot statedall-rights-reservedMapbox65696f2eadafcb1d2e7fc7e9f7c85bb923c0a3f428fb204047e0912890312cc0
Retained source material; see source provenance
Nueces County, Texas
Archived copy
Wikipedia
Other
Imported: Geometry, Imported: Recordnot statedsource-terms-not-recordedWikipedia0ed0d7e8a77cbac2e7a7200955c8f36fa3e7d34777be3d9999dc7e5e11d8dd21
Factual source record; not the publisher page
RFC 7946 GeoJSON coordinate reference system
Archived copy
IETF Trust
Company disclosure
Site distinctness context, Geometrynot statedIETF-Trust-Legal-ProvisionsIETF Trustbcaa061faa3f2f3eec2a5846b01e6986a6aacf7fa64c2e88f74fb02d260a1adf
Retained source material; see source provenance
Cite this site

Kyars, K. (2026). Hut 8 Beacon Point AI Data Center Campus [site vcc-site-a15d402305ed80ba8cba]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-a15d402305ed80ba8cba/

Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction