Microsoft Fairwater AI datacenter, Mount Pleasant

Site records

Microsoft AI supercomputing campus in Mount Pleasant, Wisconsin, on land originally slated for Foxconn. The first facility (Phase 1, near County Road KR and 90th Street) has three buildings with about 1.2 million sq ft on 315 acres; equipment came online in April 2026 and Microsoft declared it fully operational on 23 June 2026. A second facility of similar scale (Phase 2), immediately adjacent near KR and County Road H, has been under construction since November 2025 with completion scheduled for 2028. Microsoft pledged USD 3.3 billion for the first facility and USD 4 billion more for the second, and calls the site Fairwater.

This record reports partially operational as of 2026-06-23. Microsoft; Spectrum News 1

Location: Mount Pleasant, Racine County, Wisconsin, US. Microsoft's construction page headings place Phase 1 at 'KR & 90' and Phase 2 at 'KR & H' (County Road KR with 90th Street and County Road H); Spectrum News says the site was originally slated for Foxconn. Coordinates are the OpenStreetMap feature named Microsoft Fairwater AI Datacenter (via Nominatim); OSM maps Phase 2 slightly further west at about 42.6780, -87.9076. Microsoft; Microsoft; Microsoft Local; Spectrum News 1

Use: Ai training, Ai inference

Capacity, investment and other figures

MeasureValueScopeAs ofNotesSources
Investment3,300,000,000 USDAnnounced · Phase · First datacenter (Phase 1)2024-05-08Announced in May 2024 for spending through the end of 2026; Microsoft later called it the initial investment pledge, with the second datacenter funded separately.Microsoft; Microsoft On the Issues
Investment4,000,000,000 USDAnnounced · Phase · Second datacenter (Phase 2)2025-09-18Additional spend over three years on a second datacenter of similar size and scale.Microsoft On the Issues; W.Media
Investmentmore than 7,000,000,000 USDAnnounced · Campus2025-09-18Microsoft framed this as its total Wisconsin datacenter investment once the second datacenter is included.Microsoft On the Issues
Power capacityabout 369 MWOperational · Phase · It load · First facility (Epoch AI Building 1)2026-05-15Epoch AI modeled estimate of current IT power (timeline entries of April and May 2026), not a company figure. Microsoft has not published a megawatt figure for the site.Epoch AI
Land area315 acresReported · Phase · First datacenter (Phase 1)2025-09-18Official Microsoft Blog; W.Media
Buildings3 countUnder construction · Phase · First datacenter (Phase 1)2025-09-18Official Microsoft Blog; W.Media
Floor area1,200,000 sq_ftUnder construction · Phase · First datacenter (Phase 1)2025-09-18Combined floor area under roof of the three Phase 1 buildings.Official Microsoft Blog; W.Media
Jobs permanentabout 550 countReported · Phase · First datacenter (Phase 1)2026-06-23Microsoft; Spectrum News 1
Jobs permanentabout 800 countPlanned · Campus2026-06-23Expected once the second facility is fully operational.Microsoft On the Issues; Microsoft
Jobs constructionabout 10,000 countReported · Phase · First datacenter (Phase 1)2026-06-23Workers over the two-year build of the first facility; Microsoft's release says nearly 10,000.Microsoft; Spectrum News 1

Companies and organizations

NameRoleNotesSources
MicrosoftDeveloperMicrosoft; Microsoft On the Issues; Microsoft
MicrosoftOwnerEpoch AI lists Microsoft as owner.Epoch AI
MicrosoftOperatorMicrosoft reports about 550 full-time employees on site at the completed first facility.Microsoft
Walsh ConstructionBuilderNamed on Microsoft's construction update page for foundation work from November 2023 and as the Phase 2 contractor from November 2025.Microsoft Local
KiewitBuilderNamed on Microsoft's construction update page in September and October 2024 as a main contractor working along County Road KR and County Road H.Microsoft Local
We EnergiesUtilityMicrosoft cites a partnership with We Energies, and its February 2024 construction update said We Energies would soon start building a substation on the western part of the parcel.Microsoft On the Issues; Microsoft Local
National Grid RenewablesPower supplierPartner on a 250 MW Wisconsin solar project announced alongside the campus; a renewable matching arrangement rather than a stated direct feed to the site.Microsoft
NVIDIAHardware supplierMicrosoft describes the cluster as built on NVIDIA GB200 servers with Blackwell GPUs.Official Microsoft Blog
OpenAITenantReported, not confirmed: Microsoft says its AI datacenters power OpenAI, and Epoch AI lists OpenAI as a likely user of this site.Official Microsoft Blog; Epoch AI

Timeline

DateEventActual or plannedNotesSources
2023-07Construction startedActualEpoch AI dates the start of land clearing to 14 July 2023; Microsoft's update page reported permits received and grading planned from July 2023, with Walsh starting foundation work in November 2023.Microsoft Local; Epoch AI
2024-05-08AnnouncedActualMicrosoft
2024-12PausedActualThe Associated Press reported that in late December 2024 Microsoft disclosed it was pausing later phases of a large Wisconsin datacenter project.Associated Press (via News4JAX)
2025-09-18Expansion announcedActualSecond datacenter of similar size announced with an additional USD 4 billion.Microsoft On the Issues; W.Media
2025-11-01Construction startedActualStart of Phase 2 work by Walsh Construction at KR and County Road H.Microsoft Local
2026-04First operationalActualMicrosoft says equipment came online with startup activities in April 2026; Epoch AI lists Building 1 as operational on 16 April 2026. Microsoft declared the first facility fully operational on 2026-06-23.Microsoft; Epoch AI
2028OtherPlannedScheduled completion of the second facility (Phase 2); Microsoft's construction page says early 2028.Microsoft; Microsoft Local; Spectrum News 1

Power supply

TypeDescriptionSources
GridGrid supply via We Energies; Microsoft said in February 2024 that We Energies would soon start a substation on the western part of the parcel.Microsoft Local
SolarMicrosoft is matching the site with renewable contracts, including a 250 MW solar project in Portage County, Wisconsin, developed with National Grid Renewables and expected to operate in 2027.Microsoft; Microsoft On the Issues

Phase 1 and the adjacent Phase 2 are kept in one record because Microsoft describes them as adjacent facilities on one site; the later Durand Avenue and International Drive campuses approved in January 2026 have their own records. Epoch AI's projected figures for this site also fold in a 9-building plan (its Buildings 3-11), so they are not recorded here. The construction page carries month-dated entries only.

Related projects: microsoft mount pleasant durand avenue, microsoft mount pleasant international drive, microsoft fairwater atlanta