Microsoft Mount Pleasant International Drive datacenter campus
Announced
United States · 1 project · Last reported
Summary
Planned six-building Microsoft datacenter campus along International Drive in Mount Pleasant, Wisconsin, on about 530 acres Microsoft says it bought in 2024. Village planning documents reported by WPR describe more than 3.5 million sq ft of development, including a 74,000 sq ft office and other buildings, with an estimated taxable value of more than USD 5.3 billion. The plan commission recommended the site plan with conditions including a traffic impact analysis and water-use compliance, and the village board approved it unanimously in January 2026. Microsoft called the plans preliminary and gave no construction timeline or energy estimate.
Source record as of 2026-01-27 · Details and sources
Location
The interactive map needs JavaScript. Display anchor: 42.71120, -87.93390 (Point locator, WGS 84).
View location: OpenStreetMap · Google Maps · Bing aerial · Copernicus Browser
Approximate site reference; the exact facility position is unverified.
Projects (1)
Microsoft Mount Pleasant International Drive datacenter campus
Announced last observed as of · Reported status
Location: Mount Pleasant, Racine County, Wisconsin, US. Nominatim point for International Drive in Mount Pleasant, the road the sources name for the campus; the parcel boundary is not published. Wisconsin Public Radio; Spectrum News 1
Capacity, investment and other figures
| Measure | Value | Scope | As of | Notes | Sources |
|---|---|---|---|---|---|
| Investment | more than 5,300,000,000 USD | Reported · Campus | 2026-01-20 | The municipality's estimated taxable value for the development, from village planning documents reported by WPR; not a company investment figure. | Wisconsin Public Radio |
| Buildings | 6 count | Planned · Campus | 2026-01-27 | Datacenter buildings only; an office and other buildings are additional. | Wisconsin Public Radio; Spectrum News 1; Spectrum News 1 |
| Floor area | more than 3,500,000 sq_ft | Planned · Campus | 2026-01-20 | Total development size from village planning documents reported by WPR; the office and other buildings are not broken out. | Wisconsin Public Radio |
| Land area | about 530 acres | Reported · Campus | 2026-01-21 | Wisconsin Public Radio; Wisconsin Public Radio |
Companies and organizations
| Name | Role | Notes | Sources |
|---|---|---|---|
| Microsoft | Developer | Wisconsin Public Radio; Spectrum News 1 | |
| Microsoft | Owner | A Microsoft spokesperson said the land was bought in 2024; a village spokesperson said it came from the village or private owners. | Wisconsin Public Radio; Wisconsin Public Radio |
| Village of Mount Pleasant | Government | The plan commission recommended and the village board approved the site plan; the campus sits in a tax increment financing district. | Wisconsin Public Radio; Wisconsin Public Radio; Spectrum News 1 |
Timeline
| Date | Event | Actual or planned | Notes | Sources |
|---|---|---|---|---|
| 2024 | Site acquired | Actual | Wisconsin Public Radio; Wisconsin Public Radio | |
| 2026-01-20 | Announced | Actual | Site plans became public ahead of the plan commission meeting; Microsoft called them preliminary. | Wisconsin Public Radio; Spectrum News 1 |
| 2026-01-26 | Zoning approved | Actual | Plan commission recommended approval on 2026-01-21; the village board approved the site plan unanimously on 2026-01-26, allowing engineering plans and building permit applications to follow. | Wisconsin Public Radio; Spectrum News 1 |
Approved together with the nine-building Durand Avenue campus; the two campuses' combined estimated taxable value was reported as more than USD 13 billion. Microsoft told WPR that an energy-use estimate was not available.
Related projects: microsoft fairwater mount pleasant, microsoft mount pleasant durand avenue
Sources for these details
- Microsoft wants to build 15 more data centers in Mount Pleasant — Wisconsin Public Radio; 2026-01-20
- Mount Pleasant commission approves Microsoft's plans for data center expansion — Wisconsin Public Radio; 2026-01-21
- Microsoft to expand data center in Mount Pleasant — Spectrum News 1; 2026-01-21 · Archived source
- Mount Pleasant village board approves Microsoft data center expansion — Spectrum News 1; 2026-01-27 · Archived source
- Companies
- Developer: Microsoft (unknown scope) evidence
- Developer: Microsoft (unknown scope) evidence
- Owner: Microsoft (unknown scope) evidence
- Owner: Microsoft (unknown scope) evidence
- Government: Village of Mount Pleasant (unknown scope) evidence
- Government: Village of Mount Pleasant (unknown scope) evidence
- Government: Village of Mount Pleasant (unknown scope) evidence
Source and location review
- Status source
- Mount Pleasant village board approves Microsoft data center expansion evidence row
Spectrum News 1 · published 2026-01-27 · News - Locator
- Approximate site reference · Compiled location reference · approximate_site evidence
- Source checks
Not reviewed against imagery not_
reviewed
No imagery review is recorded for this project. Its status rests only on the dated authoritative source. · no independent imagery verificationStatus age at review: 273 days before the data update on 2026-10-27
Location details
- Coordinates
- 42.71120, -87.93390
- Geometry licence
- source-terms-not-recorded
- Use scope
- Approximate site reference
- Scope class
- approximate_site
- Authority
- Compiled location reference
- Source entity
- Project
- Method
- imported_reference_point
- Derivation
- imported_reference_point
- Precision scope
- Nominatim point for International Drive in Mount Pleasant, the road the sources name for the campus; the parcel boundary is not published.
- Horizontal uncertainty
Not reported
The source record provides no measured horizontal uncertainty; original coordinate precision and note are preserved.
- Geometry evidence
- 20fee728
A locator places the site on the map. It is not a building footprint, a construction extent or a surveyed boundary unless the use scope is an official boundary, and even then it is a parcel or permit boundary.
Evidence
Sources are linked, not redistributed; each keeps its own terms. An archived copy is a lookup for the Wayback Machine capture nearest the retrieval date and may be unavailable or differ from what was reviewed. Each hash states what it covers; imported factual records are not publisher-page captures.
| Title | Publisher | Roles | Published | Retrieved | Licence | Attribution | Content hash (SHA-256) |
|---|---|---|---|---|---|---|---|
| Microsoft to expand data center in Mount Pleasant Archived copy | Spectrum News 1 News | Imported: Geometry, Imported: Record, Metric: Buildings, Milestone: Announced, Role: Developer | source-terms-not-recorded | Spectrum News 1 | e09f839f30f4fb2fd9e8da293e03e7f9434cde0cc6bd75882015aefc5bdd0cf1Factual source record; not the publisher page | ||
| Microsoft wants to build 15 more data centers in Mount Pleasant Archived copy | Wisconsin Public Radio News | Imported: Geometry, Imported: Record, Metric: Buildings, Metric: Floor Area, Metric: Investment, Metric: Land Area, Milestone: Announced, Milestone: Site Acquired, Role: Developer, Role: Government, Owner claim | source-terms-not-recorded | Wisconsin Public Radio | f5c07ee2d16d30d338ec6b0749836f4293ad6b42aa12d1c2039d40ab6aa1c402Factual source record; not the publisher page | ||
| Mount Pleasant commission approves Microsoft's plans for data center expansion Archived copy | Wisconsin Public Radio News | Imported: Record, Metric: Land Area, Milestone: Site Acquired, Milestone: Zoning Approved, Role: Government, Owner claim | source-terms-not-recorded | Wisconsin Public Radio | fefa01c1b78ce4247a1c0a885f4860edcd80d717b3d09e9492ac66d4f72e0a7aFactual source record; not the publisher page | ||
| Mount Pleasant village board approves Microsoft data center expansion Archived copy | Spectrum News 1 News | Imported: Record, Imported: Status, Metric: Buildings, Milestone: Zoning Approved, Role: Government | source-terms-not-recorded | Spectrum News 1 | c9e5ab699903ee4f4c258c03a79ae4359110c1ceab118e746fe2682a669f7845Factual source record; not the publisher page |
Cite this site
Kyars, K. (2026). Microsoft Mount Pleasant International Drive datacenter campus [site vcc-site-c5988379bc974f1f6240]. In Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/sites/vcc-site-c5988379bc974f1f6240/
Show on the map explorer JSON for this site GeoJSON for this site Download dataset Report a correction