2026-10-27 · 792 sites

Atlas data archived on 2026-10-27, with additions and corrections listed below.

Summary #

Updated
Observation dates
to
Counts
792 sites, 851 projects, 63 countries, 4431 evidence rows
Previous snapshot
2026-10-27 · 776 sites
Manifest SHA-256
4e19690ea2fe49d040f46aef62133324af03bd8647c176caac283488ddac0683
Files
Download this snapshot · GitHub

Changes from the previous snapshot #

16 sites added; 2 sites changed; 17 projects added; 1 project changed; 102 evidence rows added; 9 evidence rows changed.

Sites added (16) #

Fields changed (21) #

Values that changed between the two snapshots. The earlier data remains available.

TableRecordFieldBefore → after
sitesStargate Milam County (SB Energy campus)
vcc-site-00432e4e9c8e2d91ff76
oldest_status_as_of2026-04-17 → 2026-10-01
sitesStargate Milam County (SB Energy campus)
vcc-site-00432e4e9c8e2d91ff76
newest_status_as_of2026-04-17 → 2026-10-01
sitesCompass Datacenters DFW III Campus (Red Oak)
vcc-site-5530a2d607e4a2cef4c8
project_count2 → 3
sitesCompass Datacenters DFW III Campus (Red Oak)
vcc-site-5530a2d607e4a2cef4c8
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
sitesCompass Datacenters DFW III Campus (Red Oak)
vcc-site-5530a2d607e4a2cef4c8
project_stable_keys_jsonJSON value changed (see the CSV files of both snapshots)
projectsStargate Milam County (SB Energy campus)
316e6c68-21e0-50d1-973e-d4fa5847a99f
status_as_of2026-04-17 → 2026-10-01
projectsStargate Milam County (SB Energy campus)
316e6c68-21e0-50d1-973e-d4fa5847a99f
status_age_days_at_review193 → 26
projectsStargate Milam County (SB Energy campus)
316e6c68-21e0-50d1-973e-d4fa5847a99f
status_methodimported_documented_status → authoritative_physical_status_update
projectsStargate Milam County (SB Energy campus)
316e6c68-21e0-50d1-973e-d4fa5847a99f
status_evidence_id9a99f24e-7b16-5f5e-bd04-b8657f2c12fd → 573be71c-3d31-5459-8f95-a12d1729dc20
projectsStargate Milam County (SB Energy campus)
316e6c68-21e0-50d1-973e-d4fa5847a99f
status_source_urlhttps://www.datacenterknowledge.com/data-center-site-selection/openai-expands-stargate-with-five-new-data-center-sites-… → https://web.archive.org/web/20261001050806id_/https://milamdc.com/our-commitment/
evidenceTxGIO StratMap Land Parcels: Compass Datacenters DFW III parcels, Project Cardinal-Rev and Project Cardinal II, Red Oak
0db352f1-29b4-50fd-be24-b99bf4f276e9
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceDataBank: press-release sitemap (captured 26 October 2026)
245dcbca-2e73-5d2b-8cff-2ae5113f477d
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceLoudoun County LOLA_DATA land-development applications layer definition (LOLA_PLANS_POLY)
82b7b820-1062-588d-83a0-959f2af02d3b
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceDataBank: db_data_center sitemap (facility and campus pages with lastmod times)
9fea3786-043e-5a36-87ff-2cfbd3cf88a9
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceTABS2027003697: Compass Datacenters - DFWIII-III - Building 10 - Interior / Tenant Fit Out
a547ce09-2612-54ba-904b-7543b95e7578
roles_jsonJSON value changed (see the CSV files of both snapshots)
evidenceTABS2027003697: Compass Datacenters - DFWIII-III - Building 10 - Interior / Tenant Fit Out
a547ce09-2612-54ba-904b-7543b95e7578
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceSpotsylvania County Planning Commission: agenda packet for the meeting of 21 October 2026 (Planning Department Public Hearing Cases Status Report dated 14 October 2026)
a90bc444-ff87-5554-86e8-f9521d4517a8
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceStafford County Board of Supervisors: minutes of the regular meeting of 18 August 2026 (item 19, Potomac Church Tech Center proffer amendment, ordinance O26-25)
b6153e11-1f93-5175-b824-46db9768ecba
roles_jsonJSON value changed (see the CSV files of both snapshots)
evidenceStafford County Board of Supervisors: minutes of the regular meeting of 18 August 2026 (item 19, Potomac Church Tech Center proffer amendment, ordinance O26-25)
b6153e11-1f93-5175-b824-46db9768ecba
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceTDLR TABS project search: location address 'Austin Blvd', location city Red Oak (all registration dates)
c9feec41-5210-5320-9727-e8c034123b18
project_ids_jsonJSON value changed (see the CSV files of both snapshots)
evidenceTxGIO StratMap address points: North Austin Boulevard, Red Oak (Ellis County)
fe1e9b3a-23a2-5ab4-a78b-d8a7c800f2d9
project_ids_jsonJSON value changed (see the CSV files of both snapshots)

Cite this snapshot #

Kyars, K. (2026). Data Center Atlas (2026-10-27) [Data set]. https://kiankyars.github.io/datacenter-atlas/downloads/2026-10-27-research-ninetyfirst/