2026-10-13 · 389 sites
Atlas data archived on 2026-10-13, with additions and corrections listed below.
Summary #
- Updated
- Observation dates
- to
- Counts
- 389 sites, 413 projects, 53 countries, 2038 evidence rows
- Previous snapshot
- 2026-10-13 · 198 sites
- Manifest SHA-256
f7633d08f600db61aaaf2edce5bc25c77dca654dfa28b63fde462c14d2ee0eec- Files
- Download this snapshot · GitHub
Changes from the previous snapshot #
191 sites added; 22 sites changed; 212 projects added; 11 projects changed; 1109 evidence rows added; 6 columns added or removed.
Columns #
| Table | Column | Change |
|---|---|---|
| projects | project_ | added |
| evidence | publication_ | added |
| evidence | content_ | added |
| evidence | source_ | added |
| evidence | source_ | added |
| evidence | source_ | added |
Sites added (191) #
- Abernathy HPC campus (TeraWulf and Fluidstack joint venture) vcc-site-8ea405601b72e53a6661
- ACS DC La Puebla data center campus vcc-site-5b95b2458a9a5add9fad
- AdaniConneX Hyderabad data centre campus vcc-site-42f06f3124352e4af817
- AdaniConneX Navi Mumbai data centre campus vcc-site-bb97e3ebf82c06ecfb2c
- AdaniConneX Noida data centre campus vcc-site-c4475d593124b26a70cd
- AirTrunk HYD1 Hyderabad vcc-site-2b9d83de9f69d94f5df1
- AirTrunk JHB1 vcc-site-b83e933ca77e513685ed
- AirTrunk JHB2 vcc-site-3d8ad7e35f76709e9b15
- AirTrunk JHB3 Johor Bahru vcc-site-492efa6e8a99e32cfb93
- AirTrunk JHB4 Johor Bahru vcc-site-f8df65a48b8288eac8cb
- AirTrunk Kurri Kurri Data Centre vcc-site-63d7eb757cdf71a1ae84
- AirTrunk TOK1 Tokyo East vcc-site-d3117bafca6bdcc5007e
- Aker Nscale Korgen AI data center vcc-site-35381f89404ef4c2a035
- Amazon and STACK campus at Resilient Technology Park, Shreveport vcc-site-1246c2b9750b8b4832d2
- Amazon Web Services Hobart data center campus vcc-site-c51acbb151880f9815b8
- Amazon Web Services King George County campus (Birchwood site) vcc-site-9c23979ae731456903ea
- Applied Digital Delta Forge 2 vcc-site-8d354596ddb2508a0eda
- Applied Digital Polaris Forge 3 vcc-site-5af95dd1d26b0546ea7f
- Art Data Centres Ennis campus vcc-site-a94efdae4ca44082dd5e
- atNorth DEN02 Varde mega site vcc-site-e5d89f88732b72ed1705
- atNorth FIN05 Salo mega site vcc-site-3b04bcaab24c7214a619
- atNorth NOR01 Haugaland mega site vcc-site-7b9b287883c887b86116
- atNorth SWE04 Sollefteå mega site vcc-site-424c62f417d6e6ef2c93
- AWS Clinton data center (former Delphi plant) vcc-site-0819a764e96ce06f14c6
- AWS Fayette County data center site vcc-site-04c2489b55d49bcb5ef5
- AWS Lake Anna Technology Campus vcc-site-6547aae0762f92e98a07
- AWS New Carlisle data center campus (Project Rainier) vcc-site-6835cf832163c1403b4e
- AWS Richmond County data center campus vcc-site-9b47e002ec40fe02a2d7
- AWS Vicksburg data center campus vcc-site-ab1cba1760d42b280cd1
- Balico gas-powered data center campus, Pittsylvania County vcc-site-7b36022a26fba8770036
- Beacon AI Centers Heartland campus (Sturgeon County) vcc-site-5376b585718a989c8dc5
- Beacon AI Centers Indus campus vcc-site-ef8be5d9da9f69e72683
- Bell AI Fabric Sherwood campus (Regina area) vcc-site-0834945607ed54e349ce
- Bitdeer and Geis Shalersville AI data center campus vcc-site-43a4fd4202a0c1c9518f
- Bitdeer Clarington data center site vcc-site-4551992e6d4d1487d1ab
- Bitdeer Fox Creek energy and computing facility vcc-site-63cd8442296ed3e4fc36
- Bitdeer Weathersfield (Niles) development site vcc-site-755524c9fd6de6eed9f2
- Box2Bit Epilon data center campus (Épila) vcc-site-60428cb258a38898ef68
- Bridge Data Centres Chonburi hyperscale campus vcc-site-8345f1f9d37238aa593f
- Bridge Data Centres MY06, Sedenak Tech Park vcc-site-18b5f6f9e4309fa610af
- Bridge Data Centres MY07, Ulu Tiram vcc-site-9d88c072bfebf964cf3a
- Brookfield AI center, Strängnäs vcc-site-6548266e7ea8549844f6
- Campus AI Fouju vcc-site-27b404b316b5fece1ef1
- Cavour Hyperscale Campus (Trino) vcc-site-a4bfb4274cc4e48492b6
- Cipher Barber Lake data center vcc-site-ad9a83cc2040a19f7750
- CloudHQ GRU Campus (Paulínia) vcc-site-68fa7b1f6e39bd438e45
- CloudHQ QRO Campus (Querétaro) vcc-site-9209936dfd95900f78c3
- Compass Datacenters Hoffman Estates campus vcc-site-b2e02b9541ac2f2a5b20
- Compass Datacenters Meridian campus vcc-site-4c3f2c7b887170cea7c1
- Core Scientific Denton data center (CoreWeave) vcc-site-dadea001f97aa8058f7a
- Core Scientific Hunt County data center site vcc-site-684f1565a0f48756e238
- Core Scientific Muskogee data center campus vcc-site-bf829ea21a9d7386fb5f
- CoreWeave Kenilworth NEST 11 AI data center vcc-site-7ceb4cfa4ba358ea4547
- Crusoe Abilene AI factory campus for Microsoft vcc-site-9f7647940a58e048e38f
- Crusoe and Lancium Childress AI data center campus vcc-site-5cc5c2b2cb554d5a3255
- Crusoe and Tallgrass AI data center campus near Cheyenne (Project Jade) vcc-site-f6a2889114e99d84b372
- CtrlS Chandanvelly AI-ready data center park vcc-site-7a48afbd332e0560f535
- CyrusOne Bosque County data center campus (Thad Hill) vcc-site-119a6992bb6bb25cc011
- CyrusOne Freestone County data center campus vcc-site-4776103546341c240223
- Data4 Cambrai E-Valley campus vcc-site-14a570a5f1dfb8b45e8d
- Data4 Escaudain campus vcc-site-3b5d1fe13cf00d04d3f2
- Data4 Hanau campus vcc-site-4a5d5083c6a8b110c612
- DataVita Lanarkshire AI Growth Zone campus (Chapelhall) vcc-site-ad58c35abfe93060c2c2
- DataVolt Oxagon AI data centre campus (NEOM) vcc-site-a55b68896de9ae43657e
- DayOne Chonburi Tech Park (CTP) data center campus vcc-site-b020cba78b5fa2123866
- Deutsche Telekom Industrial AI Cloud, Munich Tucherpark vcc-site-9bb64eeea962a4cadd06
- EcoDataCenter 2 Borlänge campus vcc-site-ce3b42e4fc2f6b33b8a2
- EdgeConneX Greater Osaka campus (Kagoya Tatara Campus, Kyotanabe) vcc-site-6fbf2c20aeb106991c61
- EdgeCore Louisa County campus vcc-site-ebc20ddd515fd9367ea7
- EdgeCore Mesa data center campus vcc-site-54d4a697323404ecfc35
- Eni and Khazna AI data center campus, Ferrera Erbognone vcc-site-47f902912a847a235f3d
- Fermi America Project Matador campus vcc-site-0fd145d30136b16a75ed
- G42 and Microsoft Olkaria geothermal data centre campus vcc-site-e7f4d963829eac6090a7
- Google Armstrong County data center campus (Crusoe Goodnight) vcc-site-9da1382c1df4f319ef97
- Google Cedar Rapids data center campus (Big Cedar Industrial Center) vcc-site-5878345369c98c058193
- Google Fort Wayne data center vcc-site-e2ec9daea00e4e3d9dc1
- Google Franklin Township data center proposal (Project Flo) vcc-site-65784844ad2a20822ec7
- Google Journey data center campus (Haskell County) vcc-site-e348a191d95cf61970ae
- Google Kansas City data center campus (Hunt Midwest Business Center) vcc-site-210a7753dcf05471886c
- Google Meitner Energy Center data center (Gray and Roberts counties) vcc-site-7b3778f58b65d557b1f9
- Google Stillwater data center campus vcc-site-d92255df1f2246ac16d5
- Google Waltham Cross data centre vcc-site-078fc4166e995b536458
- Google West Memphis data center campus vcc-site-1c393b2e71d64f0ffd69
- Green IT Aragón data center campus (SAMCA), Luceni vcc-site-0d25d33c7b8c51f70ba3
- Herbata data centre campus (Naas) vcc-site-d1b09eaeac654b3c56f6
- Hexagon Data Center (Riyadh) vcc-site-ba5a5fcafa0e68a3bbc8
- Homer City Energy Campus vcc-site-f49882717c93278a3c62
- HUMAIN Al-Saad hyperscale AI data centre campus vcc-site-a226e4ce3df02dee4be7
- HUMAIN Dammam AI data centre vcc-site-8f9f601fd64ed7dfc62c
- Igoudar Dakhla green data centre complex vcc-site-1057cda1149b646f7a24
- Iozera Tetouan AI data center and hub vcc-site-4b620bcac790d6755738
- IREN Childress data center campus vcc-site-b80c969b486b2844a8d9
- IREN Kiowa data center campus vcc-site-f19474c4631ae00b2725
- Joliet Technology Center vcc-site-d98cef70ec1688f58e42
- K2 hyperscale data center campus, Zibido San Giacomo and Lacchiarella vcc-site-4cde3223014097681c99
- Kasi Cloud LOS campus (Lekki, Lagos) vcc-site-94afbf6dc84e8a88fc00
- Khazna Data Centers Dammam campus vcc-site-74a60737ad3cfc9e9a75
- Khazna QAJ1 AI data center (Ajman) vcc-site-284562d636d49db446ea
- KIO Data Centers QRO3, Querétaro vcc-site-8626707eb0091306e3b9
- La Osa Energy Center (Vermaland), Pinal County vcc-site-2890b11431bd73672216
- Lambda Kansas City AI factory vcc-site-e305b394a907f57f2639
- Meta Beaver Dam data center vcc-site-fcfc181b3d5d02fb0a65
- Meta Bowling Green data center vcc-site-a39bc0fe88ed4e44ee52
- Meta Cheyenne data center vcc-site-a51d60551e72a6720e31
- Meta DeKalb Data Center vcc-site-560ea7139f27238b7ea1
- Meta Gallatin Data Center vcc-site-beb10377588af430b5a6
- Meta Kansas City data center vcc-site-60b38ee835b4579aa5f2
- Meta Kuna Data Center vcc-site-d80966c9e0bc776042e6
- Meta Mesa Data Center vcc-site-cb8ab0ad35bb603ea3ba
- Meta Montgomery data center vcc-site-4905a5572ec5f3fc6e2d
- Meta New Albany data center campus (Prometheus) vcc-site-66e95eb80a122bb2ee32
- Meta Talavera de la Reina data center campus vcc-site-2972c6d36048ca1770e2
- Meta Temple Data Center vcc-site-6afd5a936ac72410543b
- Meta Tulsa data center vcc-site-4ed4b7a2d6d92a9362bb
- Microsoft La Muela datacenter campus (Aragón) vcc-site-155a753d051b04508b1c
- Microsoft Middenmeer Campus West expansion (Agriport Plot B) vcc-site-04be359939cf11193024
- Microsoft Mount Pleasant Durand Avenue datacenter campus vcc-site-c9f14a3df329db2670d8
- Microsoft Mount Pleasant International Drive datacenter campus vcc-site-c5988379bc974f1f6240
- Microsoft Pecos datacenter campus vcc-site-91ad5264ef3af020a0ed
- Microsoft Skelton Grange datacentre campus, Leeds vcc-site-307be41074d784035ee5
- Microsoft Union City data center campus (EdgeConneX) vcc-site-deed58b28fabd02848f5
- Microsoft Villamayor de Gállego datacenter campus (Aragón) vcc-site-b74f3c274a5a8c1e01da
- Microsoft Zaragoza (Puerto Venecia) datacenter campus vcc-site-1e165cace19ab3a9b463
- Mihta Askiy Data Centre vcc-site-499a1602728034c6a587
- Morris Technology Park vcc-site-6e1076932d6836b39df9
- National AI Computing Center, Solaseado (Haenam) vcc-site-af1774a8d4eb3398e76e
- Nebius Birmingham AI factory (Lakeshore Parkway) vcc-site-8cdb2274a5a7f5abf1c9
- Nebius Independence AI factory vcc-site-acf731facf63970bd84b
- New Hill Digital Campus vcc-site-ff3fe91dbbe9f9beaf9e
- NEXTDC S7 Sydney vcc-site-dd0f231b23c8dd96495b
- NTT Global Data Centers Tokyo TKY12 campus, Shiroi vcc-site-627bed0b413c9b712d70
- Old Ocean Data Center (Nightpeak Energy) vcc-site-88d9a98c0d66b0ceae9f
- Page, Arizona data center site (Huntley LLC) vcc-site-09a8ea20931b50e7a218
- Pennsylvania Digital I (PAX-1), Middlesex Township vcc-site-07b3e2197c23d98b282e
- PowerHouse 95 data center campus vcc-site-6d5fe2fc2166ad27899f
- PowerHouse Grand Prairie campus (PowerHouse and Provident) vcc-site-910b8939869a2f993425
- PowerHouse Louisville hyperscale campus (Camp Ground Road) vcc-site-f7c2acac6f50afd8adde
- Princeton Digital Group JC3 Greater Jakarta vcc-site-99d9ae40e299f5a9f017
- Princeton Digital Group JC4 Greater Jakarta vcc-site-c606ab687ab04588148a
- Project Blue vcc-site-18500c4557e6b208669d
- Project Sail (Prologis data center campus, Coweta County) vcc-site-fcd641148c4f61598efc
- Prometheus Hyperscale Evanston campus vcc-site-a393d0e2bc6a6f9efbd5
- PW Digital Gateway vcc-site-cd315d5cbb01f749da8f
- QTS and Lancium Hall County data center campus vcc-site-990a491f49bc3fcbf938
- QTS Calatorao data center campus vcc-site-62511f2ff7c107b083ea
- QTS Eemshaven data center campus vcc-site-5c6aac8d35554558a1fc
- QTS Fayetteville campus vcc-site-32a95caf9128d7dd56c8
- QTS Vimercate data center campus vcc-site-e6669b76221d6e79fd89
- Quantum Frederick data center park vcc-site-bf298971fe1dec3fc0ac
- Red Admiral data centre campus, Rochfortbridge vcc-site-a2932dfc186e6f2538c8
- Reliance Jamnagar AI-enabled data centre for Meta vcc-site-7f644893d8685d1d4b44
- Rio AI City (Elea Data Centers) vcc-site-72339650a9d5c93e8286
- Riot Platforms Corsicana facility vcc-site-387901bd13edd6eab35d
- Rowan Project Temple vcc-site-998792d68106140776c0
- Scala AI City (Eldorado do Sul) vcc-site-a1239f397b785f28fd31
- Scala Data Centers Tamboré Campus vcc-site-36fd6f2f441272102aa1
- Sify Chennai 02 data center campus, Siruseri vcc-site-dc7beeb061c0e039f4cf
- Sify Noida 02 data center campus vcc-site-37108b4d9d3683d6451d
- Sify Rabale data center campus (Mumbai 03), Navi Mumbai vcc-site-2088ce1cae4288c3f3a1
- SK AI Data Center Ulsan vcc-site-e8f2d5efccb035e9135a
- SoftBank Hokkaido Tomakomai AI Data Center vcc-site-6fc591eaf0edc175a75c
- SoftBank Osaka Sakai AI data center vcc-site-d9155165962c78be00da
- SoftBank-Sesterce Bosquel AI data center vcc-site-6bf2ad82353d1ed7d3c9
- STACK Infrastructure Berry Hill campus, Pittsylvania County vcc-site-e6ad7f75be14475fcc3b
- Stargate Milam County (SB Energy campus) vcc-site-00432e4e9c8e2d91ff76
- Stargate UAE / UAE-US AI Campus vcc-site-401adc8a0db451b1d581
- STT Fairview data center campus vcc-site-78bd59a55f0376662286
- Synapse Data Center (Olds) vcc-site-7a7046b12f3789bb93a5
- Taylor Technology Campus (Big Watt Digital and PowerHouse) vcc-site-450769770dfe5ea908d6
- TBC Partners Cambois data centre campus vcc-site-b3a2be1a532755abcfa9
- TCS HyperVault AI data center campus, Bharat Future City (Hyderabad) vcc-site-23fd4beb18c498caa043
- TeraWulf Chesapeake Data Campus (Morgantown) vcc-site-6a1efb9a8859fd17aa59
- TeraWulf Justified Data campus (Hawesville) vcc-site-dbe568d910290db51ead
- TeraWulf Lake Hawkeye data campus vcc-site-a291a33ca480670cccf1
- TeraWulf Muskie Data Campus vcc-site-133b0abe4851d7ed6df5
- Terranova Campinas data centre campus vcc-site-c2bcc9c77043eec23331
- Terranova Praia Grande data center campus (proposed) vcc-site-3a91e1c2ee3ef8dbd116
- Teton Digital Black Bear power and data centre campus (Swan Hills) vcc-site-50ba6e2d0f69faaff629
- Tillion Aragón data center campus (Azora), Villamayor de Gállego vcc-site-6bd6515ae5d1dc80cf5a
- Tract Buckeye data center park vcc-site-7cb4c635a0469cf8e507
- Vantage Data Centers Cyberjaya II campus (KUL2) vcc-site-54113ebec20f61dd4a6e
- Vantage Data Centers Johor campus (JHB1), Sedenak Tech Park vcc-site-d70371ee13abb96e26fb
- Vantage Data Centers Villanueva de Gállego campus vcc-site-028ea637886484fbc894
- Vantage Frontier campus (Stargate Shackelford County) vcc-site-f3c14c6227b2ae418664
- VIRTUS Wustermark campus vcc-site-dba81c9003e655831d45
- WBS Power Baltic Data Center Campus, Lublewo vcc-site-cd3c4380161bc1c0389f
- Wonder Valley AI data centre park (Alberta) vcc-site-0a62731022d2820e105f
- xAI Colossus 1 (Memphis) vcc-site-837c77c61e73b3c11714
- xAI Colossus 2 (Memphis) vcc-site-62e42a722eab77bd5345
- xAI MACROHARDRR data center (Southaven) vcc-site-64d29806f5007969e3b9
- YTL Green Data Center Park, Kulai vcc-site-ebacb890726508925a40
Fields changed (160) #
Values that changed between the two snapshots. The earlier data remains available.
| Table | Record | Field | Before → after |
|---|---|---|---|
| sites | Applied Digital Polaris Forge 1 Campus vcc- | project_ | 1 → 2 |
| sites | Applied Digital Polaris Forge 1 Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Applied Digital Polaris Forge 1 Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Applied Digital Polaris Forge 1 Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Applied Digital Polaris Forge 1 Campus vcc- | newest_ | 2026-07-27 → 2026-10-07 |
| sites | Applied Digital Polaris Forge 1 Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Applied Digital Polaris Forge 1 Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QScale Q01 Lévis Campus vcc- | project_ | 1 → 2 |
| sites | QScale Q01 Lévis Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QScale Q01 Lévis Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QScale Q01 Lévis Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QScale Q01 Lévis Campus vcc- | newest_ | 2026-06-04 → 2026-10-09 |
| sites | QScale Q01 Lévis Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | QScale Q01 Lévis Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Hut 8 River Bend AI Data Center Campus vcc- | project_ | 1 → 2 |
| sites | Hut 8 River Bend AI Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Hut 8 River Bend AI Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Hut 8 River Bend AI Data Center Campus vcc- | newest_ | 2026-08-04 → 2026-10-05 |
| sites | Hut 8 River Bend AI Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Hut 8 River Bend AI Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Nscale Kvandal Narvik AI Data Center Campus vcc- | project_ | 1 → 2 |
| sites | Nscale Kvandal Narvik AI Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Nscale Kvandal Narvik AI Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Nscale Kvandal Narvik AI Data Center Campus vcc- | newest_ | 2026-07-06 → 2026-09-02 |
| sites | Nscale Kvandal Narvik AI Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Nscale Kvandal Narvik AI Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Meta Richland Parish Data Center vcc- | project_ | 1 → 2 |
| sites | Meta Richland Parish Data Center vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Meta Richland Parish Data Center vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Meta Richland Parish Data Center vcc- | oldest_ | 2026-07-16 → 2026-07-14 |
| sites | Meta Richland Parish Data Center vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Meta Richland Parish Data Center vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Riot Rockdale Campus vcc- | project_ | 1 → 2 |
| sites | Riot Rockdale Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Riot Rockdale Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Riot Rockdale Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Riot Rockdale Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Riot Rockdale Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Galaxy Helios Data Center Campus vcc- | project_ | 1 → 2 |
| sites | Galaxy Helios Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Galaxy Helios Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Galaxy Helios Data Center Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Galaxy Helios Data Center Campus vcc- | newest_ | 2026-07-06 → 2026-08-12 |
| sites | Galaxy Helios Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Galaxy Helios Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | AdaniConneX Pune Data Center Campus vcc- | project_ | 1 → 2 |
| sites | AdaniConneX Pune Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | AdaniConneX Pune Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | AdaniConneX Pune Data Center Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | AdaniConneX Pune Data Center Campus vcc- | newest_ | 2026-06-01 → 2026-07-29 |
| sites | AdaniConneX Pune Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | AdaniConneX Pune Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | STT Jakarta Data Centre Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Cipher Digital Black Pearl Wink Data Center Campus vcc- | project_ | 1 → 2 |
| sites | Cipher Digital Black Pearl Wink Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Cipher Digital Black Pearl Wink Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Cipher Digital Black Pearl Wink Data Center Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Cipher Digital Black Pearl Wink Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Cipher Digital Black Pearl Wink Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | project_ | 1 → 2 |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | newest_ | 2026-06-02 → 2026-07-28 |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Core Scientific Pecos Cottonwood Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | project_ | 1 → 2 |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | oldest_ | 2026-06-30 → 2026-01-19 |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | NEXTDC M4 Melbourne Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Applied Digital Polaris Forge 2 Campus vcc- | project_ | 1 → 2 |
| sites | Applied Digital Polaris Forge 2 Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Applied Digital Polaris Forge 2 Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Applied Digital Polaris Forge 2 Campus vcc- | newest_ | 2026-07-27 → 2026-10-07 |
| sites | Applied Digital Polaris Forge 2 Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Applied Digital Polaris Forge 2 Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | project_ | 1 → 2 |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | newest_ | 2026-06-04 → 2026-10-05 |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Lancium Clean Campus Abilene AI Data Center vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | TeraWulf Lake Mariner Data Campus vcc- | project_ | 1 → 2 |
| sites | TeraWulf Lake Mariner Data Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | TeraWulf Lake Mariner Data Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | TeraWulf Lake Mariner Data Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | TeraWulf Lake Mariner Data Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | TeraWulf Lake Mariner Data Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | OMNIA Pecém Data Center Campus vcc- | project_ | 1 → 2 |
| sites | OMNIA Pecém Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | OMNIA Pecém Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | OMNIA Pecém Data Center Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | OMNIA Pecém Data Center Campus vcc- | oldest_ | 2026-06-16 → 2026-05-18 |
| sites | OMNIA Pecém Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | OMNIA Pecém Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Hut 8 Beacon Point AI Data Center Campus vcc- | project_ | 1 → 2 |
| sites | Hut 8 Beacon Point AI Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Hut 8 Beacon Point AI Data Center Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Hut 8 Beacon Point AI Data Center Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Hut 8 Beacon Point AI Data Center Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Amazon Salem Township Innovation Campus vcc- | project_ | 1 → 2 |
| sites | Amazon Salem Township Innovation Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Amazon Salem Township Innovation Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Amazon Salem Township Innovation Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Amazon Salem Township Innovation Campus vcc- | newest_ | 2026-07-19 → 2026-10-09 |
| sites | Amazon Salem Township Innovation Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Amazon Salem Township Innovation Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | DataOne Vineland Two-Phase AI Data Center Facility vcc- | project_ | 1 → 2 |
| sites | DataOne Vineland Two-Phase AI Data Center Facility vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | DataOne Vineland Two-Phase AI Data Center Facility vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | DataOne Vineland Two-Phase AI Data Center Facility vcc- | newest_ | 2026-08-07 → 2026-10-09 |
| sites | DataOne Vineland Two-Phase AI Data Center Facility vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | DataOne Vineland Two-Phase AI Data Center Facility vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QTS Cambois Data Centre Campus vcc- | project_ | 1 → 2 |
| sites | QTS Cambois Data Centre Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QTS Cambois Data Centre Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QTS Cambois Data Centre Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | QTS Cambois Data Centre Campus vcc- | newest_ | 2026-07-01 → 2026-08-06 |
| sites | QTS Cambois Data Centre Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | QTS Cambois Data Centre Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Microsoft Mount Pleasant Datacenter Campus vcc- | project_ | 1 → 2 |
| sites | Microsoft Mount Pleasant Datacenter Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Microsoft Mount Pleasant Datacenter Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Microsoft Mount Pleasant Datacenter Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Microsoft Mount Pleasant Datacenter Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Microsoft Mount Pleasant Datacenter Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Start Campus Sines Data Campus vcc- | project_ | 1 → 2 |
| sites | Start Campus Sines Data Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Start Campus Sines Data Campus vcc- | project_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Start Campus Sines Data Campus vcc- | statuses_ | JSON value changed (see the CSV files of both snapshots) |
| sites | Start Campus Sines Data Campus vcc- | newest_ | 2026-06-23 → 2026-08-03 |
| sites | Start Campus Sines Data Campus vcc- | verification_ | recent_authoritative_physical_observation_plus_reviewed_site_locator → mixed_review_postures |
| sites | Start Campus Sines Data Campus vcc- | imagery_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Google / Beale Tulsa County Project Clydesdale Campus Construction 0a4a2c40- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Google / Beale Tulsa County Project Clydesdale Campus Construction 0a4a2c40- | operator | empty → Google |
| projects | CDC Marsden Park Early Construction 164033cb- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | CDC Marsden Park Early Construction 164033cb- | owner | empty → CDC Data Centres |
| projects | Meta Lebanon Indiana Current Development 1f430ea1- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Meta El Paso Current Development 337ace90- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Meta El Paso Current Development 337ace90- | owner | empty → BlackRock (managed funds); Meta Platforms |
| projects | Meta El Paso Current Development 337ace90- | tenants | empty → Meta Platforms |
| projects | Vantage Lighthouse Port Washington Current Campus Build 3b636397- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Vantage Lighthouse Port Washington Current Campus Build 3b636397- | owner | empty → Vantage Data Centers |
| projects | Vantage Lighthouse Port Washington Current Campus Build 3b636397- | tenants | empty → OpenAI; Oracle |
| projects | Oracle Project Jupiter Doña Ana County Current Campus Build 6f0acd88- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Oracle Project Jupiter Doña Ana County Current Campus Build 6f0acd88- | tenants | empty → OpenAI; Oracle |
| projects | The Barn Stargate Current Data Center Build 7d936c4e- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | The Barn Stargate Current Data Center Build 7d936c4e- | tenants | empty → OpenAI; Oracle |
| projects | Lübbenau Data Center Current Build 8f5c2434- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Lübbenau Data Center Current Build 8f5c2434- | operator | empty → STACKIT |
| projects | Lübbenau Data Center Current Build 8f5c2434- | tenants | empty → Baden-Württemberg Police; Kaufland; Lidl |
| projects | Delta Forge 1 Current Construction b7744ad5- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Meta Sturgeon County Alberta Current Campus Build d1538d73- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Google Elmina Current Campus Construction e56ff51f- | role_ | JSON value changed (see the CSV files of both snapshots) |
| projects | Google Elmina Current Campus Construction e56ff51f- | operator | empty → Google |
| projects | Google Elmina Current Campus Construction e56ff51f- | tenants | empty → Google |
Cite this snapshot #
Kyars, K. (2026). Data Center Atlas (2026-10-13) [Data set]. https://kiankyars.github.io/datacenter-atlas/downloads/2026-10-13-consolidated/